Forthcoming Works in Area 4
Coulsdon Road
As part of SGN mandatory gas
replacement scheme there continues to be 2 way or multi way signals along Coulson
Road. It is
planned to commence the renewal of the gas service pipes as from the 24.8.2020
this follows agreement with SGN for entry into residential properties on
condition that strict observance of the social-distancing, wearing of PPE
clothing and consent of the residents are complied with. The first section will
involve the re-introduction of 4 way traffic signals at the junction with The
Crossways – Coulsdon Road – Keston Avenue, It is essential that this section be
completed prior to the re-opening of schools in September. Work will continue
in Coulsdon Road with the re-introduction of side road closures, this will
allow for the use of 2 Way traffic signals.
Tennison Close
which is the final phase of work on Coulsdon Road is provisionally scheduled to
commence on the 10th August 2020, this will be subject to the
progress being made with the service renewal on the Coulsdon Road – Tollers
Lane programme.
Rydons Lane
is the last phase of these two projects. Due to the narrowness of the road a
traffic order has been applied for to close the road. This work is scheduled to
commence on 24th August and
expected to be completed in 6 weeks. All properties to be visited for
discussions with residents for access to carry out the renewal of their gas
service pipe.
Lacey Drive
With the continued road closure at its junction with Coulsdon Road this
has allowed for considerable progress to be made. All the gas service pipes
will be renewed and the permanent re-instatement will be completed by the 1st
August 2020. The road closure and bus diversion will be re-opened on that date.
Pampisford Road
Work has commenced on the
final section of open trenching to the junction with Kendra Hall Road, all
service pipes have been laid from the replacement main and laid commissioned to
a capped end in the footway / verge. The permanent reinstatement of the
carriageway is up to date. The outstanding completion of the service pipes
renewal (from the footway / verge) into the residential properties has yet to
be confirmed, as and when this takes place, but it is hoped to be before the
schools go back in September. The works
will be not need further incursion into the carriageway
St Augustines Avenue
As part of SGN mandatory gas
mains replacement scheme, St Augustine’s Avenue will reopen on Monday 3rd
August
Purley Way
SGN will be starting a gas
mains replacement scheme from its junction with Mill Lane to Waddon Court Road from 22nd July.
For the first phase Waddon Road will be closed at its junction with Purley Way
and Purley Way and Mill Lane will be controlled with three way signals. This
phase is expected to be completed on 5th August although the whole
scheme is expected to take 10 weeks. All remaining phases will be carried out without the
further use of temporary traffic signals.
Waddon Road
SGN will be starting a gas
mains replacement scheme in Purley Way, from its junction with Mill Lane to
Waddon Court Road, from 22nd July. For the first phase Waddon Road will be
closed at its junction with Purley Way and Purley Way. This is expected to be
reopened on 5th August.
Old Lodge Lane/Hayes Lane
To facilitate gas mains
replacement work SGN will be closing the junction of Hayes Lane and Old Lodge
Lane from 27th July to 5th August. Whilst the restriction
is in force the diversion routes for traffic will be via Hayes Lane, Park Road, A22, and Burntwood
Lane (and vice versa) or via Old Lodge Lane, A23, and A22
Brighton Road, Purley
Thames Water are working on a
water leak outside The Pear Tree for which they are using two way temporary
signals. They have been instructed to manually control the lights at peak
times. This work should be completed by 5th August
Sussex Road
Sussex Road will be closed on
two consecutive Sunday 2nd and 9th August to facilitate a
new gas connection. Whilst the closure is in place the diversion routes for
traffic will be via Moreton Road, Croham Road, Croham Manor Road and Selsdon
Road and vice versa, or via Sussex Road and Selsdon Road.
Selsdon Road
Thames Water will be making use
of buses being on diversion to carry out a new service connection at the
northside junction with Sussex Road. They will be using multi way signals to
facilitate the repair on Sunday 2nd August
Foxley Lane
SGN will be using 2 way temporary
signals to facilitate their work for a new service connection 3rd to
10th August. The signals will be manually controlled at peak times
to ease traffic flows
Pitlake
To complete a gas mains
replacement scheme SGN will be using two way temporary signals to control the
traffic, outside numbers 36 to 38, which will be manually controlled through
the morning and evening peak times. This work will commence on the 3rd
and be completed by the 11th August.
Coulsdon Road
To facilitate an urgent repir
on a link box UKPN will be using two way temporary signals near the junction
with Tennison Close from 4th to 7th August
Parsons Mead
To facilitate a new water
connection Thames Water will be using two way temporary signals to control the
traffic outside number 10 from 4th to 11th August
Hill Road
To facilitate a new service
connection SGN will be using two way lights from 7th to 13th
August
Waddon Road
Thames Water will be using 4
way temporary signals at the junction of Waddon Road/Waddon New Road/Epsom Road
from, 8pm to 5am each evening, from 10th to 14th August
to facilitate the laying of a new service pipe.
Hollymeoak Road
To facilitate the installation
of a correlation point SESW will be using two way temporary signals from 10th
14th August
Riddlesdown Road
To facilitate a new service
connection outside number 80, SGN will be using two way temporary signals from
10th to 18th August
Selsdon Road
SGN will be starting a gas
mains replacement scheme from its junction with St Peters Road to Drovers Road
from 3rd August to 2nd September. To facilitate these
works there will be three way lights on the roundabout and Croham Road will be
one way from the roundabout to St Peters Street
Brighton Road, Coulsdon
SESW will be making Brighton
Road one way southbound between its junctions with Farthing Way and The Avenue
from 17th to 20th August. The diversion for displaced
traffic will be via Farthing Way and Brighton Road, or via Smitham Downs Road,
Woodcote Grove Road and Brighton Road,
Abbotts Lane
To facilitate a new service
connection SGN will be using 2 way signals to control the traffic, outside
number 51, from 17th to 24th August
Selsdon Road Bridge
To carry out enabling work for
the forthcoming bridge replacement Selsdon Road will be closed on Sunday 6th
September, from 7am to 7pm, between its southernmost junction with Sussex Road
and its junction with Chelsham Road. The diversion route for traffic will be
via St Peter’s Road, Coombe Road, South Park Hill Road, Croham Road and
Addington Road